Producten — ankerdataset1060 events · peil 2026-11-27

Producten

15 ankerproducten van de hardwarecrisis. Per product: trendlijn uit de tijdseries (alleen waar ≥2 datapunnen), events en leverancierssignalen uit 1060 events.

01

NVIDIA B200 GPU

30 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: 20 MW -> 84 MW planned with GB300 NVL72 liquid-cooled racks; on-site fuel cells bypass incremental utility interconnect, >US$7B committed Texas AI-server capacity; Pegatron already in GB200/GB300 shipment from Texas, ABF substrate, ASML EUV, Advanced packaging, Board design, CXMT HBM3E yield still 20–30% vs SK hynix ~70%; Jinhua capacity insufficient for Huawei demand, CoWoS capacity

02

GB300 / DGX Station

17 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: 144x800G CPO ports per switch deployed across >10,000 GPUs; 4x fewer lasers per port than pluggable optics, 20 MW -> 84 MW planned with GB300 NVL72 liquid-cooled racks; on-site fuel cells bypass incremental utility interconnect, 9-CSP CapEx: $957B 2026 (+106%) → >$1.5T 2027 (+60%, revised up from 50%), 9-CSP capex: $957B 2026 (+106%) -> >$1.5T 2027 (+60%); AI server shipments +32.2% 2026, +~36% 2027, >US$7B committed Texas AI-server capacity; Pegatron already in GB200/GB300 shipment from Texas, ASML EUV, Advanced packaging, CoWoS packaging

03

HBM3e geheugen

43 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: 1-gamma process would match or exceed Samsung/SK Hynix 1X-class nodes for HBM4E performance targets, 71% market share = extreme concentration risk. If Hanmi experiences production disruption (fire, labor dispute, export restriction), HBM4 assembly at all three memory vendors is constrained simultaneously., ABF substrate, AI demand growth, ARM ecosystem maturity, Advanced packaging, Both HBM3E suppliers raising prices simultaneously indicates collective capacity constraint rather than competitive undercutting, CXMT HBM3E yield still 20–30% vs SK hynix ~70%; Jinhua capacity insufficient for Huawei demand

04

HBM4 geheugen

72 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: 1-gamma process would match or exceed Samsung/SK Hynix 1X-class nodes for HBM4E performance targets, 1.8 MW/CDU in-row cooling at N+1; NVL72 rack = 20.7 TB HBM4; scalable-unit blueprint to GW scale, 100%-liquid NVL72 racks plus fanless NVL8 trays each require in-rack/manifold CDU capacity and OCP quick-disconnect inventory per node — direct demand signal for CDU, cold-plate and UQD suppliers through 2027 Rubin ramp., 321L >50% of domestic NAND capacity in 4Q26; M15X maxed end-2026; Yongin P1 full op 2027; 14 LTAs cover >half of memory capacity, 5 HBM lines, KRW 46T (6T fab + 40T equipment), +150,000 sqm floor area at Onyang; Onyang+Cheonan plan raised to KRW 60T, 70% allocation = structural moat for SK Hynix; base die yield respin a known risk factor, 71% market share = extreme concentration risk. If Hanmi experiences production disruption (fire, labor dispute, export restriction), HBM4 assembly at all three memory vendors is constrained simultaneously., 8-Hi HBM4 requires fresh NVIDIA certification of already-qualified vendors; HBM4E mass-production timing (Samsung: 1H27 plan) is the offsetting variable

05

CoWoS advanced packaging

42 events in dataset

TSMC CoWoS capacity by end-2026 (two-source spread, flagged discrepancy) 2 meetmomenten — geen trendlijn88 → 127,5 wafers/month
9010011012088127,52026-12-012026-12-01
TSMC CoWoS die size in reticles3,3 → 5,5 reticles
455,52026-10-15
TSMC CoWoS yield 2 meetmomenten — geen trendlijn98 → 98 %
9898982026-05-182026-10-15

Signalen: $1.3T hyperscaler capex in 2027 implies continued GPU procurement at or above current pace — supports long-term CoWoS/HBM demand projections., $161.2B aggregate rent under Broadcom master equipment leases + additional TPU compute procurement committed for 2028-2031 delivery (S-1), 5.5x-reticle CoWoS in HVM at 98–99% yield; 14x target 2029, 6 GW cumulative Anthropic TPU deployment planned through 2027, ABF substrate, AI GPU (Blackwell/Rubin), server-CPU and custom-ASIC packaging demand; test-time growth consuming assembly/test capacity; upstream equipment delivery (6-8 months), Advanced packaging, Advanced packaging equipment

06

ABF-substraat

10 events in dataset

Ibiden ABF substrate size (largest side) 2 meetmomenten — geen trendlijn90 → 130 mm
90100110120130901302026-09-10

Signalen: ABF substrate, CoWoS packaging, Grid power, HBM3e memory, Ibiden, Kinsus ABF capacity for NVIDIA >3.5x current with new lines in 2H27; SPIL packaging agreement; Samsung Electro-Mechanics substrate + Amkor US/Korea expansion support, Nippon Steel, Planning horizon extended to 3–5 years across fab + packaging + substrates

07

DDR5 RDIMM

41 events in dataset

Conventional DRAM contract price change, quarter-on-quarter94 → 12,5 %
25507512,52026-01-012026-10-01
Samsung DRAM ASP change, quarter-on-quarter90 → 20 %
20406080202026-01-012026-07-01
DDR5 chip-level price 2 meetmomenten — geen trendlijn6,8 → 27,2 USD
10206,827,22025-09-012025-12-01
Server DRAM price index (ServnetUK, 2025-Q3=100) 2 meetmomenten — geen trendlijn100 → 527 index
2004001005272025-07-012026-07-01

Signalen: 1.8 MW/CDU in-row cooling at N+1; NVL72 rack = 20.7 TB HBM4; scalable-unit blueprint to GW scale, 23% of DRAM wafers now dedicated to HBM (up from 8% in 2024); no major new DRAM fab capacity before 2028, 2Q26 DRAM revenue share table: Samsung 39.4 / SK hynix 24.9 / Micron 23.3 / CXMT 9.5 (%), 33% LPDDR capacity cut on a flagship AI-edge platform — first hard evidence memory costs are resizing BOMs at the high end of the demand curve, 4F² 6th-gen platform validated on wafers; DDR5 RDIMM server samples targeted by end-2026, >1M Maia 300 accelerators planned for 2027 at 96 chips/~167 kW per rack — incremental liquid-cooled rack demand outside the NVIDIA ecosystem, >50% more gross die per wafer at 8Gb-equivalent vs G4; LPDDR5X 24Gb products (50% more data vs prior gen), Advanced packaging

08

eSSD (enterprise SSD)

36 events in dataset

NAND contract price change, quarter-on-quarter57,5 → 17,5 %
20406017,52026-01-012026-10-01
2TB NVMe street price 2 meetmomenten — geen trendlijn120 → 300 USD
1502002503001203002024-06-012026-06-24
8GB eMMC price 2 meetmomenten — geen trendlijn1,5 → 20 USD
51015201,5202025-07-012026-02-17

Signalen: 2027 NAND industry CapEx US$29.9B (+26.7% YoY); bit supply growth 25–30% YoY 2027, 256TB in a single E3.S slot (QLC), plus PCIe Gen6 SSD shown, 3.93PB in 2U (32x E3.S 122.88TB Gen6 drives) demonstrated shipping, 321-layer NAND to ~50% of domestic capacity by end-2026; Yongin P1 cleanroom early 2027 adds new capacity; H1 2026 cumulative revenue >100T won for first time, 321L >50% of domestic NAND capacity in 4Q26; M15X maxed end-2026; Yongin P1 full op 2027; 14 LTAs cover >half of memory capacity, 512TB in E2 form factor demonstrated; Gen6 drives to sample 1Q27, Addresses the controller CPU scaling wall for PCIe Gen6+ high-capacity eSSDs (incl. 245TB-class QLC drives), Capacity allocation shifts to HBM/server DDR5/enterprise QLC; some makers booked through 2028

09

Nearline HDD

37 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: +100% Toshiba HDD capacity by FY2027 on ~$380M capex (Philippines), 10x capex factor over ~next year; hardware allocations secured, shipments ahead of schedule; CoreWeave minimum ramps through mid-2027, 195 EB/quarter nearline to data centers (+43% YoY); nearline = 89.4% of shipped capacity, 209 EB nearline shipped in single quarter (Q2 FY2026). Hyper-concentration on cloud (>89% revenue) creates hyperscaler dependency risk but secures committed volumes., 220 EB shipped; record 198 EB nearline datacenter; LTAs majority of nearline EB through CY2028, some cloud agreements through CY2030; HAMR ~50% of nearline run-rate exiting CY2026, 248 EB shipped, +21.6% Y/Y; 40TB ePMR at 50% of nearline by FQ3 FY27; 44TB HAMR volume shipments CY1H 2027, 40TB ePMR volume at customer. 44TB HAMR H1 CY27 on track. LTA negotiations covering 2029 to 2031 in active progress. Exabyte growth greater than 25% guided forward., All 2026 nearline capacity allocated. NVMe $/TB ratio 16x from 6x YoY. Consumer HDD approximately 5% of WD output. HDD price rise 35-46% YoY.

10

800G / 1.6T transceivers

99 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: $115B by 2027 implies ~$57B compound growth from FY2025 baseline; networking and interconnect represent an increasing share as GPU-count-per-cluster grows non-linearly, $16.7B AI semiconductor revenue in single quarter = ~$67B annualized rate; bandwidth of demand far exceeds historical networking TAM, $53.6B Ethernet adapter/SmartNIC TAM by 2030, $600M+ optical revenue target for FY2027 across AEC, DSP, and optical engine product lines; suggests optical segment alone approaching $300M+ annually, 100G+ EML capacity held by exactly 4 vendors (Lumentum 50-60%); 200G EML wafer yields 10-20% for some products, 10MW on-site AI validation lab + 1.6T Ethernet switch design program at Penang, 12.8 Tb/s per OSFP-sized module; 4x front-panel density vs 200G/lane pluggables, 144x800G CPO ports per switch deployed across >10,000 GPUs; 4x fewer lasers per port than pluggable optics

11

Transformatoren

45 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: $1.84B+ announced across 7 US plants in 8 weeks; earliest production 2028 (Southwire) / 2029 (Hitachi Gallman), $34.5M Shreveport transformer capacity expansion, ~+30% workforce, full production by 2028, $34.5M transformer capacity expansion, +175 direct jobs at Shreveport, LA, $340M transformer production expansion (Jonesville SC), in addition to Eaton's September $242M Arkansas enclosure plant, $800M H1 2026 US transformer orders, $9B acquisition adds 11 plants + a new Charlotte 765 kV line (output late 2027) to GEV Electrification; ~$5B backlog/frameworks (into the 2030s), +$5B Trench backlog/frameworks folded into GEV Electrification; GEV total backlog $197B→>200B Q4, +1.1 GW near-term firm capacity from existing fleet; UPRISE program now ~4.7 GW identified vs 5-GW target

12

Grid-interconnect

231 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: $1.5B annual liquid cooling revenue base from Boyd Thermal adds ~5K employees across NA/EU/Asia; Eaton's combined power + cooling scale creates #2 position after Vertiv, $1.84B+ announced across 7 US plants in 8 weeks; earliest production 2028 (Southwire) / 2029 (Hitachi Gallman), $100B 5-yr plan; 84 GW contracted load through 2031; ~9.6 GW of new 765-kV capacity for one campus, $115B by 2027 implies ~$57B compound growth from FY2025 baseline; networking and interconnect represent an increasing share as GPU-count-per-cluster grows non-linearly, $2.6B total potential consideration signals how expensive 'time to power' has become; complements Eaton↔Siemens Energy modular onsite-power partnership, $200M 2027 capacity spend; quarterly capex doubling $25M→$50M; DC = 15% of Electrical segment sales, $200M combined announced DOE uplift awards in October 2026 (reconductoring/DLR + AK line), $25B 2027-2030 plan (+$2B); 645 MW CCGT (COD Q2 2032); ~50 GW prospective large-load pipeline KY+PA

13

CDU / vloeibare koeling

74 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: $1.5B annual liquid cooling revenue base from Boyd Thermal adds ~5K employees across NA/EU/Asia; Eaton's combined power + cooling scale creates #2 position after Vertiv, $900M capex program; new plant capacity 'within 12 months'; 500 MW distributed edge compute plan for 2027, +$259.5M / >400 jobs across KY+PA+OH incl. named data-center cooling manufacturing (Ohio line, est. Jul-2026 $30M), +150% modular hydronic/electric plant production capacity, Phoenix facility 17,750 m2, +500,000 sq ft US manufacturing for liquid cooling systems and chillers, production started Jun 2026, 1.8 MW/CDU in-row cooling at N+1; NVL72 rack = 20.7 TB HBM4; scalable-unit blueprint to GW scale, 100% liquid-cooled reference architecture shifts all new Rubin builds to DLC; Motivair (Schneider) cited as a long-standing design partner on the roadmap, 100%-liquid NVL72 racks plus fanless NVL8 trays each require in-rack/manifold CDU capacity and OCP quick-disconnect inventory per node — direct demand signal for CDU, cold-plate and UQD suppliers through 2027 Rubin ramp.

14

Server CPU / OEM

193 events in dataset

SEMI global semiconductor equipment billings, quarterly 2 meetmomenten — geen trendlijn36,5 → 40,5 USD billion
3738394036,540,52026-03-312026-06-30

Signalen: $1.2B named rack order; >$3B FY26 AI-networking orders guided; Helios ramp starts FY27, $104B NVIDIA revenue booked via Singapore entity in 2025 — SEA is now a compliance chokepoint, not a workaround, $3.45B equity raise + FY26 outlook raise to $21.0B revenue: equity-funded AI-rack build capacity continues, $33.3B non-cancelable upstream commitments + $702M customer deposits QoQ, $4.565B committed to the Flex power/cloud EMS unit that books AI-infra capacity post-separation, $53.6B Ethernet adapter/SmartNIC TAM by 2030, $54B AI server backlog vs ~$8.5B/quarter run-rate implies >6 quarters of visibility for Lenovo's server lines, $942M H2-26 capex + NT$15B converts + $1.5B loan = multi-billion USD committed expansion pipeline

15

NVIDIA RTX PRO 6000 Blackwell

3 events in dataset

Nog onvoldoende datapunten voor een trendlijn (serie heeft minder dan 2 punten). Het signaal staat hieronder in de events.

Signalen: 96GB GDDR7 (DRAM supply); GB202 die at TSMC 4N, GDDR7 supply (Samsung/SK hynix/Micron) — same DRAM wafer pool being diverted to HBM for datacenter GPUs, GDDR7 supply; NVIDIA allocation across Workstation/Max-Q/Server editions, Rental supply on 9 clouds stable at $1.70–$5.50/hr (median $3.03) while purchase price doubles — buy-side scarcity not yet reflected in rental rates